Navy’s second SSV, BRP Davao Del Sur now 91% completed

From Update.Ph (Nov 27): Navy’s second SSV, BRP Davao Del Sur now 91% completed

The Philippine Navy (PN)’s second strategic sealift vessel, the BRP Davao Del Sur (LD-602), is now 91 percent complete and well in line to meet her May 2017 delivery date. This was disclosed by PN spokesperson Capt. Lued Lincuna in an interview with the Philippine News Agency in an interview Sunday.

At the moment, PT PAL (Persero) shipbuilders in Surabaya, Indonesia are now installing navigational, deck and engineering equipment on the PN’s second SSV.
 
“Ongoing installation of navigational, deck, engineering equipment. I don’t know the exact percentage of completion but for sure she will be (home in the Philippines) by May 2017,” he added.

The BRP Davao Del Sur (LD-602) was launched last Sept. 29. She is the sister ship of the BRP Tarlac (LD-601), currently the largest Filipino warship in commissioned.

BRP Tarlac was commissioned during short ceremonies at Pier 13, Manila South Harbor last June 1.
She arrived in the Philippines last May 14 after a five-day journey from PT PAL shipyard in Surabaya which started on May 9.

BRP Davao Del Sur is also a Makassar-class landing platform dock like her sister ship BRP Tarlac. Its delivery to the Philippines, is tentatively scheduled on the midpart of 2017, will complete the two-unit SSV procurement project with an approved budget contract of PHP4 billion sourced from the AFP Modernization Act Trust Fund.

Just like the BRP Tarlac, the PN’s latest SSV will serve as a floating command-and-control ship especially in the conduct of humanitarian assistance and disaster response and will also serve as a military sealift and transport vessel.