This is the query of a military observer on the 21 refurbished Huey helicopters that the government is acquiring for the Philippine Air Force for a contract price of P1.263 billion. And more than a year since the contract was awarded to the joint venture of US-based Rice Aircraft Services, Inc. (RASI) and Canadian Eagle Copters, only eight refurbished UH-1D helicopters have so far been delivered.
The remaining 13
units have already been shipped to the country but are still being refurbished
in Clark , a violation of the contract that
stipulates that delivery of all 21 second hand UH-1 helicopters should be made
within 180 days upon opening of the letter of credit (LC).
Out of the eight
units, only seven have been turned over to the Air Force, of which “four are
flyable but none are mission capable due to the absence of engine protective
parts.”
The Department of
National Defense (DND) first announced the planned acquisition of the 21
refurbished UH-1 helicopters in 2012 to boost the PAF’s combat, security and
utility, transport capability.
The project was
in the pipeline as early as 2011, when then PAF Commanding General, Lt. Gen.
Oscar Rabena, requested President Aquino for additional UH-1H helicopters.
After three
failed biddings (Dec. 4, 2012; Feb. 11, 201; and Sept. 2013) for the
procurement of the refurbished Huey fleet including Integrated Logistics
Support (ILS) package, the DND resorted to negotiated procurement.
The negotiation
was conducted on Nov. 21, 2013 with the JV of RASI and Eagle Copters as lone
participant and the contract was awarded in December 2013.
MADE IN THE PHILIPPINES
The supplier
started the “first shipment on April, 2014, while the last shipment arrived
Feb. 2015- way beyond the deadline of the contract.”
An insider
revealed that “all 21 helicopters were not refurbished at the facility of Eagle
Copters in Canada , but were
directly shipped from the facility of RASI in California ,
USA to the port of Manila
then hauled to Clark .”
Instead of
delivering fully refurbished helicopters, the supplier “hired additional
Filipino mechanics, who are all retired PAF personnel, to repair/refurbish and
assemble the helicopters”.
“That’s in
violation of the terms of reference requiring refurbishment at the qualified
facility, supposedly at the facility of Eagle Copters, Ltd.,” the Manila
Bulletin source said.
The insider also
pointed out that the Filipino mechanics hired by the supplier provided
repairs/maintenance on UH-1H when they were still in active service. Thus,
“they are not on the maintenance of UH-1D helicopters,” he stressed.
Documents
obtained by the Manila Bulletin show that by the end of the contract (Sept. 21,
2014), only two units of UH-1D were inspected and accepted by the PAF. Formal
turnover, however, was made months later.
For failure to
deliver all 21 refurbished Huey helicopters within 180 days, RASI had to pay
liquidated damages to the government starting September 22, 2014 onwards.
The failure is reportedly due to lack of available parts like engines and armor
seats, among others.
BREACH OF
CONTRACT
On June 2014, the
DND presented to media four Huey helicopters in Clark on June 2014 which at
that time were not yet turned over to the PAF and not even operational, a
Manila Bulletin source revealed.
Before Christmas
of 2014, additional four units of second hand UH-1D helicopters were accepted
and paid by the DND, net of liquidated damages.
Liquidated damages
is a penalty to be deducted from payment. The amount shall be at least equal to
one-tenth of one percent of the cost of the unperformed portion for every day
of delay. Once the cumulative amount of the liquidated damages reaches ten
percent of the amount of the contract, the procuring entity shall rescind the
contract, without prejudice to other courses of action and remedies to open it.
Another UH-1D
unit was delivered on Dec. 26, 2014 although formal turnover was made only last
month, Feb. 12.
The 8th helicopter
arrived middle of February but has not been turned over to the Air Force as of
this writing.
Of the eight
delivered UH-1D helicopters, the source said only six have been paid so far.
“Ubos na kasi ang allowed LD (liquidated damages),” he said.
“For the record,
there was no ILS package, in whole or in part, delivered during the prescribed
period,” according to the source.
The ILS package
is a list of spare parts worth P60 million which was supposed to be delivered
within 180 days. The deadline of delivery was supposed to be on or before
September 21, 2014.
http://www.mb.com.ph/widow-makers-or-air-force-assets/
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.